Morgan and Mona wind farms
Morgan – meaning “sea chief” in Old Welsh
Mona – from Ynys Môn, the Isle of Anglesey
Mona consultation
Our first stage of consultation for Mona has now closed. Thank you to everyone who took part and provided feedback about the proposals.
We are now carefully considering all of the feedback we received, alongside further technical work and environmental assessments. We’ll provide further updates as our work progresses, ahead of second consultation.
You can find out more about the proposals here.
Morgan consultation
Our first round of consultation on the Morgan offshore wind farm in collaboration for Morecambe Offshore Wind Farm and their transmission assets is running for six weeks, from 2 November to 13 December 2022.
Visit the consultation website here.
Indicative timeline
2021
Habitats Regulations Assessment by The Crown Estate (TCE)
Establish project companies
2022
Signing of Agreement for Lease with the Crown Estate
Onsite environmental studies and project planning
2023
Second stage of consultation
2024
Application for Development Consent Order (DCO), Marine License
2025
Contracts for Difference (CfD) auction for power-off take agreement
2027
Expected Final Investment Decision (FID), TCE Lease
2028
First grid connection for power export commissioning of offshore substations
2029
Expected start – Commercial Operation Date (COD)